Building Utah

Construction Projects on the Rise

May 6, 2013

Provo Recreation Center

Provo − This 160,000-square-foot recreation center facility includes a variety of amenities including a walking/jogging track, fitness equipment, leisure pool, competition pool, indoor play equipment, basketball courts, racquetball courts, drop-in child care, party rooms, and other senior and community center spaces.

Developer: Provo City Parks and Recreation

General Contractor: Layton
Construction Co., Inc.

Architect: VCBO Architecture

Engineers: Reaveley Engineers, Bush & Gudgell, ECE LLC, Heath Engineering, Earthtec Engineering

Estimated Completion: April 2013

Estimated Cost: $34 million

Utah State Hospital

Provo − This project includes the demolition of three existing buildings and construction of two replacement buildings. The Payne Building is an administration and clinical facility, and the second building will be a living center with bedrooms for pediatric patients.

Developer: State of Utah

General Contractor: Layton
Construction Co., Inc.

Architect: FFKR Architects

Engineers: Reaveley Engineers, Van Boerum & Frank, Spectrum Engineers

Estimated Completion: April 2014

Estimated Cost: $24 million

Veterans Administration Veterans’ Homes

Payson − This project includes two 103,000-square-foot, 108-bed living centers for veterans, one located in Payson and one in Ivins. The homes are a valuable asset to aging veterans. The facilities have been designed with a less institutional feel, with rooms grouped in nine 12-bed pods, with independent living for the veterans, including individual bathrooms and a community kitchen within each pod.

Developer: State of Utah and Utah Department of Veterans Affairs

General Contractor: Layton Construction Co., Inc.

Architect: Beecher Walker Architects/Naylor Wentworth Lund Architects

Engineers: BHB Engineers, JUB Engineers (Payson), Alpha Engineers (Ivins), WHW Engineering Inc., Spectrum Engineers

Estimated Completion: May 2013

Estimated Cost: $17 million each

Adobe Corporate Campus
Lehi − The first of many phases for this spacious campus was recently completed. Phase 1 consisted of a 250,000-square-foot facility with approximately 200,000 square feet of office space and 30,000 square feet of additional amenities. It is anticipated to be LEED Gold certified.

Developer: Adobe Systems, Inc.
Architect: WRNS, Pollack, GSBS
General Contractor: Okland Construction
Engineers: Ensign Engineering, Spectrum Engineering, Holmes Culley, Dunn Engineering, Colvin Engineering
Estimated Completion: Phase durations under consideration

NuSkin Innovations
Center and Corporate Campus Remodel

Provo − The new Innovations Center is a 169,000-squre-foot office building, which is connected to the Corporate Office Building by an all-glass, 60-foot-wide atrium. In addition, the entire corporate campus will have quadrupled in size with additional offices, labs, data center and parking structure.

Developer: NuSkin Eterprises
General Contractor: Okland Construction
Architect: Bohlin Cywinski Jackson

Engineers: Jones Excavation, Hunt Electric, Tech Steel, Palmer Christiansen
Estimated Completion: 2014

Thanksgiving Park Phase 4

Lehi − The 141,600-square-foot, fourth phase of six includes five floors of class A office space for tenant customization. Luxurious common areas feature mahogany wall panels above marble floors and wainscoting.

Developer: Thanksgiving Park

General Contractor: Jacobsen Construction Company, Inc.

Architect: Beecher, Walker & Associates

Engineers: Dunn & Associates, CCI Mechanical

Estimated Completion: May 2013

Estimated Cost: $12 million

Provo City Center Temple

Provo − The historic Provo Tabernacle is transitioning into the Provo City Center Temple. Preservation of the prominent exterior will be ongoing as the building is converted. Its foundation is currently being rebuilt to ultimately support a basement, two floors and an original-looking roof with five towers.

Developer: The Church of Jesus Christ Latter-day Saints

General Contractor: Jacobsen Construction Company, Inc.

Architect: FFKR Architects
Engineer(s): Reaveley Engineers, Van Boerum & Frank Associates, Envision Engineering, Bowen Collins, Inc.

Estimated Completion: Fall 2015

Central/Southern Area

Eastgate Apartments

Page 12345
Utah Business Social
UB Events View All
SAMY Awards 2015Utah Business Event
Jan 23, 2015
Utah Business magazine along with Presenting Sponsor: Griffin Hill, Premier Sponsors: The Summit ...
Forty Under 40 - 2015Utah Business Event
Feb 26, 2015
Utah Business Magazine along with Presenting Sponsors: Kirton McConkie, BIG-D Construction and Ma...
CEO of the Year 2015 ... NOMINATIONS NOW OPEN!Utah Business Event
Mar 31, 2015
CEO of the Year Nominations end - January 7, 2015. Visit: www.utahbusiness.com/nomination_item...
Community Events View All
Anatomy Sketch Night | December 18th
Dec 18, 2014
During his life, Leonardo da Vinci sketched 100's of anatomical drawings of humans and animals. ...
Sandler Management Solutions
Dec 19, 2014
Looking for a way to manage your team systematically and effectively? Sandler Management Solutio...

info@utahbusiness.com  |  90 South 400 West, Ste 650 Salt Lake City, Utah 84101   |  (801) 568-0114

Advertise with Utah Business

Submit an Event

* indicates required information
* Event Name:
Price (general):
Website (if applicable):
Coordinator's Name:
Coordinator's Email:
Coordinator's Phone:
Venue Name:
Venue Address:
Venue City:
Venue Zip:
Event Capacity:
Date(s):
to
* Event Description:
  Cancel